-
01
ingest.package
✓ SUCCEEDED
0.8 s
Yard Orchestrator · Pulled the work package for B-214 from the yard MES: 46 plates, 212 seams under WPS-117, erection tolerance 2 mm at the D1 joint, PSPC-grade ballast-tank coating, erection slot on D1 in the dock plan. Locked the qualified WPS envelope and the class scope.
-
02
twin.simulate
✓ SUCCEEDED
1 m 12 s
Ship Twin · Simulated 18 candidate weld sequences on the as-built twin with the weld-thermal surrogate, ranked on predicted distortion at the erection joint, crane reach on D1 and shift takt. Standing sequence predicts 4.2 mm; candidate #6 predicts 1.8 mm.
-
03
cut.nest
✓ SUCCEEDED
3 m 40 s
Cut-and-Profile · Released the nest for 46 plates on CL-1 with the fit-up gaps candidate #6 assumes. As-cut geometry logged per plate and handed to the panel line; material yield 91.4% against the nest plan.
-
04
weld.sequence
✓ SUCCEEDED
2 m 05 s
Panel-and-Weld · Loaded the back-step sequence for the non-critical seams on PL-2 and set heat input and travel speed inside WPS-117. Weld-pool and seam cameras streaming on 12 channels.
-
05
approve.human
◆ APPROVAL
58 s
Yard Orchestrator · Candidate #6 also re-orders two class-critical butt seams, S-31 and S-32. Sequence changes on class-critical seams stay with a human, so the step was held for the shift welding engineer and approved at 06:12:44.
-
06
inspect.fuse
✓ SUCCEEDED
continuous
Quality-and-Anomaly · Twelve weld cameras and the UT station fused at the yard edge. One porosity precursor on S-31 at 06:41 flagged and cleared by a 4% wire-feed trim inside the WPS-117 envelope; the joint was routed to UT and passed.
-
07
fair.lineheat
✓ SUCCEEDED
4 m 30 s
Fair-and-Form · Post-weld scan registered against the twin: 2.1 mm at the erection joint. Two line-heating passes planned on the inner bottom and executed by the fairing crew; re-scan read 1.8 mm, inside the 2 mm tolerance.
-
08
coat.window
✓ SUCCEEDED
continuous
Blast-and-Coat · Ballast-tank blast and first coat scheduled to a window with steel temperature 3.4 °C above dew point. Dry-film thickness read 312 µm against a 280 µm minimum on the stripe coats; PSPC evidence assembled per area.
-
09
dock.reoptimise
✓ SUCCEEDED
41 s
Schedule-and-Yard · Re-solved the D1 dock and crane plan with B-214 ready 6 hours early and a neighbouring block late: erection slot pulled forward one shift, crane G2 reassigned, no berth conflict. Planner approved the revised plan.
-
10
erect.align
✓ SUCCEEDED
1 h 48 m
Erect-and-Align · Both blocks scanned on D1 and registered against the twin; fit predicted at 1.6 mm. Shimming guidance issued to the erection crew, block landed and welded out, final scan 1.6 mm. Conformance record written: welds, scans, coating readings, approvals and class evidence for B-214.